Below are the scheduled maintenance activities of Maynilad next week, most of which will take place during off-peak hours to minimize the impact of the supply interruption on our customers.
These activities are being done as part of the company’s continuous effort to improve water services in the West Zone.
Affected customers are encouraged to store enough water for the duration of the water service interruption. Maynilad has water tankers on standby, ready to deliver water to affected areas as needed.
Upon resumption of the water service, customers should let the water flow out for a few seconds until the water clears.
| City | Barangay | From | To | Time | Activity | Location of Activity |
| Quezon City | Baesa | February 11, 2025 | February 12, 2025 | 10 p.m to 6 a.m | Pressure Test | at Quirino Highway corner L.R Pascual |
| Sangandaan | February 11, 2025 | February 12, 2025 | 10 p.m to 6 a.m | Pressure Test | at Dalsol corner Engineering | |
| Bahay Toro | February 15, 2025 | February 16, 2025 | 10 p.m to 6 a.m | Pressure Test | at General Avenue corner Tandang Sora | |
| Gulod and Sta. Monica | February 10, 2025 | February 11, 2025 | 10 p.m to 6 a.m | Network Maintenance | at Nitang and at Aguardiente | |
| February 11, 2025 | February 12, 2025 | 10 p.m to 6 a.m | Network Maintenance | at Aguardiente | ||
| February 12, 2025 | February 13, 2025 | 10 p.m to 6 a.m | Network Maintenance | at Nitang and at Aguardiente | ||
| February 14, 2025 | February 15, 2025 | 10 p.m to 6 a.m | Network Maintenance | at Nitang and at Aguardiente | ||
| February 15, 2025 | February 16, 2025 | 10 p.m to 6 a.m | Network Maintenance | at Aguardiente | ||
| February 16, 2025 | February 17, 2025 | 10 p.m to 6 a.m | Network Maintenance | at Nitang and at Aguardiente | ||
| Manila | 429, 432, 436 to 438, 440, 442, 443, 446 to 448, 450, 452, 454, 456, 461, 512 to 515 and 517 | February 10, 2025 | February 10, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Algeciras Street, Sampaloc, Manila |
| February 12, 2025 | February 12, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Algeciras Street, Sampaloc, Manila | ||
| February 14, 2025 | February 14, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Algeciras Street, Sampaloc, Manila | ||
| 268 to 273, 275, 276 and 281 to 286 | February 10, 2025 | February 10, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Jaboneros Street, Binondo, Manila | |
| February 12, 2025 | February 12, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Jaboneros Street, Binondo, Manila | ||
| February 14, 2025 | February 14, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Jaboneros Street, Binondo, Manila | ||
| 830, 832 to 834, 844 to 848, 851, 855 to 857 and 859 | February 10, 2025 | February 10, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Labores Street, Pandacan, Manila | |
| February 12, 2025 | February 12, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Labores Street, Pandacan, Manila | ||
| February 14, 2025 | February 14, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Labores Street, Pandacan, Manila | ||
| 1 to 3, 7 to 9, 56 to 60, 62 to 64, 74 and 75 | February 10, 2025 | February 10, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Moriones Street, Tondo, Manila | |
| February 12, 2025 | February 12, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Moriones Street, Tondo, Manila | ||
| February 14, 2025 | February 14, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Moriones Street, Tondo, Manila | ||
| 383, 390 to 408, 410 to 412, 414 to 416, 420, 430, 433, 435, 457 and 460 | February 10, 2025 | February 10, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Recto Avenue, Santa Cruz, Manila | |
| February 12, 2025 | February 12, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Recto Avenue, Santa Cruz, Manila | ||
| February 14, 2025 | February 14, 2025 | 12 a.m to 3 a.m | Leak Exploration | at Recto Avenue, Santa Cruz, Manila | ||
| Obando City | Paco | February 10, 2025 | February 10, 2025 | 12 a.m to 3 a.m | Strainer Cleaning | at Felo 1, Rincon |
| February 11, 2025 | February 11, 2025 | 12 a.m to 3 a.m | Interconnection | at M. Reyes, Marulas | ||
| February 12, 2025 | February 12, 2025 | 12 a.m to 3 a.m | Interconnection | at Pili Street, Balangkas | ||
| February 13, 2025 | February 13, 2025 | 12 a.m to 3 a.m | Interconnection | at Mangosteen Street, Balangkas | ||
| February 14, 2025 | February 14, 2025 | 12 a.m to 3 a.m | Interconnection | at Gladiola Street, Marulas | ||
| Valenzuela City | Arkong Bato, Balangkas, Bignay, Bisig, Coloong, Dalandanan, Gen. T. De Leon, Isla, Lawang Bato, Lingunan, Mabolo, Malanday, Malinta, Maysan, Palasan, Parada, Pariancillo Villa, Pasolo, Poblacion, Polo, Punturin, Rincon, Tagalag, Viente Reales and Wawang Pulo | February 10, 2025 | February 10, 2025 | 12 a.m to 3 a.m | Strainer Cleaning | at Felo 1, Rincon |
| February 11, 2025 | February 11, 2025 | 12 a.m to 3 a.m | Interconnection | at M. Reyes, Marulas | ||
| February 12, 2025 | February 12, 2025 | 12 a.m to 3 a.m | Interconnection | at Pili Street, Balangkas | ||
| February 13, 2025 | February 13, 2025 | 12 a.m to 3 a.m | Interconnection | at Mangosteen Street, Balangkas | ||
| February 14, 2025 | February 14, 2025 | 12 a.m to 3 a.m | Interconnection | at Gladiola Street, Marulas | ||
| February 10, 2025 | February 10, 2025 | 12 a.m to 3 a.m | Strainer Cleaning | at Felo 1, Rincon |