Below are the scheduled maintenance activities of Maynilad next week, most of which will take place during off-peak hours to minimize the impact of the supply interruption on our customers.
These activities are being done as part of the company’s continuous effort to improve water services in the West Zone.
Affected customers are encouraged to store enough water for the duration of the water service interruption. Maynilad has water tankers on standby, ready to deliver water to affected areas as needed.
Upon resumption of the water service, customers should let the water flow out for a few seconds until the water clears.
| City | Barangay | Activity | Schedule | Location of Activity |
| Caloocan | Brgy. 36, 39, 189 to 191, 193, 194 and 196 | Network Maintenance | 11:01 p.m. to 3:00 a.m. daily, from March 29 to April 5, 2026 | Rizal Avenue |
| Manila | Brgy. 586, 587, 592, 593 and 600 | Network Maintenance | 10:00 p.m. of March 29, 2026 to 4:00 a.m. of March 30, 2026 | Old Sta. Mesa corner Teresa |
| Brgy. 48 to 55, 155, 160, 221 to 349, 353 to 382, 492 to 497 and 500 | Network Diagnostic / Leak Localization | 10:00 p.m. of March 30, 2026 to 6:00 a.m. of March 31, 2026 | Raxabago Street | |
| Brgy. 569, 570 and 578 to 581 | Network Maintenance | 10:00 p.m. of March 30, 2026 to 4:00 a.m. of March 31, 2026 | Manga Avenue | |
| Brgy. 32, 34, 35, 42, 45, 46, 48, 50 to 53, 55, 77, 81 to 83, 86, 87, 89 to 93, 124, 128, 131 to 136, 138 to 140, 146, 155, 177 to 183, 198 to 207, 209 to 211, 213, 216, 217, 219 to 225, 227 to 229, 231, 232, 292, 294 to 301, 303 to 310, 311, 315, 353 to 356, 359, 360, 363 to 369, 373, 374, 377, 378, 380, 382, 492, 524, 525, 529, 532, 533, 535, 649, 835 to 840 and 865 | Network Diagnostic / Leak Localization | 11:01 p.m. to 3:00 a.m. daily, from March 29 to April 5, 2026 | Binondo, Hermosa, Pandacan, Raxabago Street, Sampaloc, Santa Cruz and Tondo | |
| Brgy. 147 to 149, 151, 152, 163, 169 to 171, 396 to 404, 430, 457 and 460 | Network Diagnostic / Leak Localization | 12:01 a.m. to 3:00 a.m. daily, from March 30 to April 5, 2026 | Recto Avenue and Tondo | |
| Quezon City | Greater Fairview, North Fairview and Sta. Monica | Network Maintenance | 10:00 p.m. of March 30, 2026 to 8:00 a.m. of March 31, 2026 | Commonwealth Avenue near Fairlane |
| Valenzuela | Gen. T. De Leon, Karuhatan, Malinta, Marulas, Maysan and Parada | Network Maintenance | 12:01 a.m. to 4:00 a.m. daily, from March 30 to April 3, 2026 | Diam Street, Maysan Road and Pasong Balite |
| Pinalagad, Prodon Street and Tongco | ||||
| Cayetano Street, Independence Street and Molave Street | ||||
| Demetillo Street, Pinagbayanan and San Francisco Street | ||||
| A. Pablo Street, Bernardino and Lingunan | ||||
| Arkong Bato, Balangkas, Bisig, Isla, Mabolo, Malanday, Malinta, Palasan, Pariancillo VIlla, Pasolo, Poblacion, Polo, Rincon, Tagalag and Wawang Pulo | Network Maintenance | 10:00 p.m. to 5:00 a.m. daily, from March 31 to April 1, 2026 | Pasolo Road | |
| Obando | Paco | Network Maintenance | 10:00 p.m. to 5:00 a.m. daily, from March 31 to April 1, 2026 | Pasolo Road |