Below are the scheduled maintenance activities of Maynilad next week, most of which will take place during off-peak hours to minimize the impact of the supply interruption on our customers.
These activities are being done as part of the company’s continuous effort to improve water services in the West Zone.
Affected customers are encouraged to store enough water for the duration of the water service interruption. Maynilad has water tankers on standby, ready to deliver water to affected areas as needed.
Upon resumption of the water service, customers should let the water flow out for a few seconds until the water clears.
| City | Barangay | Activity | Schedule | Location of Activity |
| Caloocan | Brgy. 165 | Network Diagnostic / Leak Localization | 10:00 p.m. from January 25, 2026 to 6:00 a.m. of January 26, 2026 | Lugmoc Road |
| Brgy. 36, 39, 189 to 191, 193, 194 and 196 | 11:01 p.m. to 3:00 a.m. daily, of January 25, 2026 to February 1, 2026 | Rizal Avenue | ||
| Las Piñas | Almanza Dos (Ayala Southvale & Versailles) | Interconnection | 10:00 p.m. of January 25, 2026 to 5:00 a.m. of January 26, 2026 | Daang Hari corner Champaca |
| 5:00 p.m. of January 26, 2026 to 5:00 a.m. of January 27, 2026 | ||||
| 5:00 p.m. of January 27, 2026 to 2:00 a.m. of January 28, 2026 | ||||
| Almanza Dos (BF Almanza and T.S Cruz Subdivision) | 10:00 p.m. to January 25, 2026 to 2:00 a.m. of January 28, 2026 | |||
| Malabon | Dampalit and Hulong Duhat | Several Network Maintenance Activities | 10:00 p.m. of January 28, 2026 to 6:00 a.m. of January 29, 2026 | Womens Club corner Naval Street, Brgy. Hulong Duhat |
| Manila | Brgy. 51, 504, 512, 587 to 591, 600, 601, 603, 605, 610 to 612, 614 to 616, 619 and 621 | Several Network Maintenance Activities | 10:00 p.m. from January 25, 2026 to 4:00 a.m. of January 26, 2026 | Valenzuela corner V. Mapa |
| Brgy. 32, 34, 35, 42, 45, 46, 48, 50 to 53, 55, 77, 81 to 83, 86, 87, 91 to 93, 124, 128, 131 to 136, 138 to 140, 146, 155, 177 to 183, 198 to 207, 209 to 211, 213, 216, 217, 219, 221 to 225, 227 to 229, 231, 232, 292, 294 to 301, 303 to 311, 313, 315, 353 to 356, 359, 360, 363 to 369, 373, 374, 377, 378, 380, 382, 492, 524, 525, 529, 532, 533, 535, 649, 835 to 840, 865 | Network Diagnostic / Leak Localization | 11:01 p.m. to 3:00 a.m. daily, from January 25 to February 1, 2026 | Bindondo, Hermosa Street, Pandacan, Raxabago Street, Sampaloc, Santa Cruz and Tondo | |
| Brgy. 147 to 149, 151, 152, 163, 169 to 171, 396 to 404, 430, 457 and 460 | Network Diagnostic / Leak Localization | 12:01 a.m. to 3:00 a.m. daily, from January 26 to February 1, 2026 | Recto Avenue and Tondo | |
| Muntinlupa | Poblacion (NHA Phase 1 to 4) | Interconnection | 10:00 p.m. of January 25, 2026 to 5:00 a.m. of January 26, 2026 | Daang Hari corner Champaca |
| Tunasan (Diamond, Emerald Hills, Jade Heights, Pearl Heights, Ruby Park, Sapphire Heights and Victoria Homes) | 5:00 p.m. of January 26, 2026 to 5:00 a.m. of January 27, 2026 | |||
| 5:00 p.m. of January 27, 2026 to 2:00 a.m. of January 28, 2026 | ||||
| Poblacion (NBP Area, NBP Max, NBP Min, MCX and Promiseland) | 10:00 p.m. to January 25, 2026 to 2:00 a.m. of January 28, 2026 | |||
| Valenzuela | Bagbaguin, East Canumay, Mapulang Lupa, Paso De Blas and Ugong | Several Network Maintenance Activities | 10:00 p.m. of January 29, 2026 to 6:00 a.m. of January 30, 2026 | Sto. Rosario Street corner P. Salad, Brgy. Mapulang Lupa |
| Bacoor | Aniban I | Network Diagnostic / Leak Localization | 10:00 p.m. from January 30, 2026 to 4:00 a.m. of January 31, 2026 | Narra Street corner E. Aguinaldo Highway |